Bitcoin miner Riot Platforms sold more than 10,599 Bitcoin in the third quarter of 2026, causing the company’s holdings to fall from 11,380 to 2,418 Bitcoin, a decrease of almost 79%. The proceeds are being used to build data centres. At the same time, Riot signed a $28 billion contract with an unnamed AI lab for 910 megawatts of data centre capacity in Corsicana, Texas.

In brief:

  • Riot sold a total of 20,264 Bitcoin in the first nine months of 2026 for approximately $1.5 billion.
  • Quarterly revenue was $181 million, but profit fell sharply compared with a year earlier.
  • The company has now contracted a total of 1,151 megawatts of data centre capacity, representing around $38 billion in long-term contracted revenue.

Significant Bitcoin sales to finance data centres

Riot Platforms, the second-largest listed Bitcoin miner in the world, announced its financial results for the third quarter of 2026 on Wednesday. The company sold 10,599 Bitcoin in that period. That brought total sales in the first nine months of this year to 20,264 Bitcoin, generating approximately $1.5 billion.

Quarterly revenue was $181.4 million, an increase of 1% compared with a year earlier. Net profit, however, fell to $4 million, compared with $104 million in the same quarter last year. Revenue from Bitcoin mining fell by around 28% year on year to $116 million.

Riot ended the quarter with $950.2 million in cash and Bitcoin. The company says it has not raised any new equity through share issuance in 2026.

$28 billion deal with AI lab in Corsicana

The biggest announcement in the quarterly report is a 15-year lease with an unnamed Frontier AI Lab. It covers Riot’s entire Corsicana campus, a contiguous site of 332 hectares with 910 megawatts of IT capacity. The total contract value is around $28 billion, with average annual rental revenue of $1.8 billion during the initial contract term.

CEO Jason Les says that with this deal and earlier contracts, Riot has now leased 1,151 megawatts of data centre capacity, representing a total of $38 billion in long-term contracted revenue. At full occupancy, the company expects to generate more than $2 billion in average annual net operating income.

Les also points to the relatively low capital cost of the Corsicana project: around $6 million per IT megawatt, roughly half of what a comparable Tier 3 data centre would cost. Partly for this reason, Riot currently sees no need to issue additional shares to finance its ongoing projects. How the company will allocate the growing contract income between new investments and returning capital to shareholders remains open for now, according to Les.

Summarize this article with AI

Not financial advice. The Latest Crypto News provides educational and informational content only. Crypto-assets are highly volatile and you can lose your entire investment. Always do your own research. Read our full disclaimer.

Affiliate disclosure. Some links on this site are affiliate links. If you sign up with a partner through one of them, we may earn a commission at no extra cost to you. This never influences our reporting. See our editorial guidelines.

More Mining News

More news ›